How to Prepare a Commercial Glazing RFQ: A Property Manager's Checklist

Why three glazing bids on the same opening come back uncomparable, and the RFQ line items — scope track, glass make-up, working hours, securing, engineering, measurement trigger — that make them comparable again.
Most commercial glazing bids are not difficult to price. They are difficult to compare. Three contractors walk the same lobby, and three proposals come back with different glass make-ups, different assumptions about working hours, different positions on who provides engineering, and one lump sum each. The owner picks the low number, and four weeks later the low number has grown by the exact amount of everything that was never written down.
The fix is not a longer bid form. It is a request for quotation that names the conditions clearly enough that every bidder is pricing the same job. This guide sets out what a commercial glazing RFQ should contain, what each item protects you from, and how to read the responses when they come back. It is written for property managers, building owners, facility teams and general contractors on the Colorado Front Range, and it assumes no glazing background.
One framing note before the checklist. Glazing contractors measure, coordinate, order and install; the glass, framing and hardware are produced by manufacturers and fabricators. Abricos Glass works that way, and we say so on every proposal. It matters to an RFQ because most schedule risk lives in the product order rather than in the labour, and an RFQ that asks the right questions about the product is an RFQ that produces a realistic date.
RFQ line items and what each one protects you from
| RFQ item | What to ask for | What it prevents |
|---|---|---|
| Scope track | State whether you expect service, lite replacement or system replacement | Bids priced against three different jobs |
| Glass make-up | Require the bidder to name build, coating and spacer in writing | A cheap clear lite quietly substituted for a coated insulated unit |
| Hardware | Name closers, pivots, thresholds and locks by function and duty | Default hardware that fails early on a high-cycle entrance |
| Working hours | State trading hours and whether after-hours work is expected | After-hours premiums arriving as a change order |
| Securing | Ask how a broken opening is secured and when measurement happens | A board-up treated as the repair, then a second mobilisation |
| Engineering and permits | Name who produces, submits and pays for each | An unassigned stamped drawing stalling the order |
| Measurement trigger | Ask what must be final on site before field measurement | A remeasure after tile, curb or framing changes the opening |
| Assumptions and exclusions | Require all three headings on the proposal | Lump sums that move after award |
Start by naming the scope track
Almost every commercial glass scope belongs to one of three tracks: service the existing assembly, replace the glass and keep the frame, or replace the system. Bidders who disagree about which track they are on will produce numbers that cannot be compared at all, so state your working assumption in the RFQ and invite bidders to contest it.
If you are not sure which track applies, say that too, and ask for a field review before pricing. A contractor who prices a distorted, corroded frame as a straightforward lite replacement is not cheaper — they are describing a different job than the one you have.
Reactive work versus planned capital
Reactive work is a break, a failed door, a security exposure. It is priced for speed and disruption, and the useful RFQ question is how the opening gets secured and what sets the replacement date.
Planned capital work is a survey, a budget and a phased programme. Here the useful question is different: what does the contractor recommend replacing now, what can be deferred a season, and what evidence supports that split? Mixing the two in one RFQ is the most common reason a bid package produces unusable answers.
The information every bidder needs
The following list is what lets a glazing contractor price without padding. Each missing item is replaced by an assumption, and assumptions are always priced conservatively.
Property address, suite and a site contact who can grant access. Photographs of the full elevation as well as the affected opening — the elevation shows the system, the close-up shows the damage. Approximate opening sizes measured corner to corner. Whether the glass is single-pane or an insulated unit. A photograph of any tempering stamp etched in a corner, which tells the bidder what the original lite was. Frame type and visible condition. Interior or exterior, and which floor.
Then the conditions that shape labour rather than product: whether the space is occupied and its trading hours, access constraints such as lifts, loading docks, badge or escort rules, protected landscaping or sidewalk restrictions, and any building rules about noise windows or hot work. Finally, the commercial frame: your target schedule, who holds the permit if one is needed, and whether drawings or a glass and glazing specification section exist.
Specify the glass, or ask the bidder to
Glass make-up is the single largest driver of both price and lead time, and it is where bids diverge most quietly. Clear tempered, laminated, insulated and coated units are not substitutes for one another, and a coated unit matched to an existing elevation is a made-to-order item with a real lead time behind it.
If you know the make-up, state it. If you do not, do not guess — ask each bidder to state the make-up they have priced, in writing, including coating and spacer where an insulated unit is involved. A proposal that names its glass build can be compared to another proposal that names its glass build. A proposal that says 'replace glass' cannot be compared to anything.
The same applies to hardware on an entrance scope. Closers, pivots, thresholds, locks and panic devices should be named by function and duty rather than left to the installer's default, because door hardware is what fails first on a busy commercial frontage.
Ask who owns engineering, permits and review
Where a scope requires structural calculations or stamped documents — glass guards are the usual case — someone has to produce and submit them. That responsibility belongs in the proposal, named explicitly, not settled by conversation after award. Engineering, when required, is produced by a licensed engineer.
The same holds for permits and for design review. Work on a property in a designated historic area may attract landmark or design review by the local authority, and whether it applies is confirmed for the specific address and scope. Requirements vary with the adopted code edition, occupancy, building height, the approved project documents, and the Authority Having Jurisdiction, so treat any contractor's code discussion as background rather than as a determination.
Write the schedule question properly
'How fast can you do it?' produces an optimistic number from every bidder and useful information from none. Two better questions: what is the lead time on the specific product you have priced, and when is it confirmed? And what has to be true on site before you can field measure?
Tempered glass cannot be cut, drilled or resized after fabrication, which is why measurement comes after the surfaces the glass bears on are final — tile, curb, cap, deck fascia, frame. An RFQ that asks bidders to name their measurement trigger will surface the ones who intend to measure from drawings.
Require scope, assumptions and exclusions
The most valuable page in any glazing proposal is the one listing what is not included. Substrate reinforcement by others, patching and painting, temporary securing, after-hours premiums, disposal, permit fees, engineering, access equipment and finish carpentry are all common exclusions, and all of them become change orders when they are left unstated.
Ask each bidder for three headings: scope, assumptions, exclusions. Bids that carry them can be levelled line by line. Bids that do not are lump sums that will move.
How to level the responses
Put the bids side by side and compare on five axes before price: the glass make-up named, the working hours assumed, the securing plan, the responsibility split for engineering and permits, and the measurement trigger. Differences on any of those explain most price gaps you will see.
Then look at what each bidder self-declares. A contractor who states plainly that they do not fabricate in house is telling you where their schedule risk sits and who they depend on. That is more useful than a claim of end-to-end capability that cannot be verified.
Finally, treat any published cost range — including ours — as budgeting guidance rather than a quote. Front Range pricing depends on field measurement, access, glass make-up, hardware, quantities and schedule.
Frequently asked questions
- What is a commercial glazing RFQ?
- A request for quotation is the document you send to glazing contractors describing the opening, the conditions and the commercial terms you want priced. Its purpose is not to specify how the work is done but to make sure every bidder prices the same job, so the responses can be compared line by line.
- Do I need drawings to request commercial glass pricing?
- Not for most repair and replacement scopes. Photographs of the full elevation and the affected opening, approximate dimensions, frame type and access details are usually enough for a field review to be scheduled. Drawings and a glass and glazing specification section shorten the process considerably on larger or new-system scopes.
- Why do glazing quotes vary so much on the same opening?
- Usually because the bidders have assumed different glass make-ups, different working hours, or a different split of responsibility for engineering, permits and securing. Requiring each bidder to state those in writing removes most of the spread before you look at price.
- Should the price change after field measurement?
- It can, and an honest proposal says so up front. A pre-measurement figure is scoped from photographs and stated dimensions; the firm price follows the field measurement, because tempered glass cannot be resized after fabrication and the frame condition is not visible in a photograph.
- Who is responsible for engineering on a glass guard scope?
- Where a project requires calculations or stamped documents, that requirement and its owner should be named in the written proposal. The engineering itself is produced by a licensed engineer. Requirements vary with the adopted code edition and the Authority Having Jurisdiction.
Planning a glass project?
We measure, coordinate fabrication, and install across the Denver metro and the Front Range. Send us your dimensions or photos and we'll come back with a clear, itemized quote.
Request a quote →Related pages
- Commercial glass for property managers and building owners
- Commercial glass company in Denver
- Storefront glass repair in Denver
- Commercial storefront glass contractor in Fort Collins
- Interior glazing and office partitions
- Commercial doors, entrances and windows
- Glass railings and guards
- Request a commercial glazing quote